Total ongoing projects: 87 |
||||||||
|---|---|---|---|---|---|---|---|---|
| Project Type | Project Name | Start Year End Year |
Approved Cost & Cumulative Expenditure (Lakh Tk.) |
District | Upazila | Constituency | Status | Download |
| OTHERS | Rehabilitation Polder's (No. 67/A, 67, 67/B & 68) along border river of Naf for Improving Bangladesh & Mayanmar Security at Ukhia & Teknaf Upazila in cox's Bazar District (2nd Revised) |
FEB-18 JUN-27 |
41,558.05 22,257.02 |
COX'S BAZAR | TEKNAF, UKHIA | Cox's Bazar-4 | On Going | Download |
| FLOOD CONTROL, DRAINAGE AND IRRIGATION | Flood Control Drainage Improvement and Water Logging mitigation of Chittagong City (1st Revised) |
APR-19 JUN-27 |
150,838.01 145,326.98 |
CHATTOGRAM | HATHAZARI, KOTWALI | Chattogram-5, Chattogram-9 | On Going | Download |
| OTHERS | Small-scale watercraft procurement project to enhance the capacity of the Ministry of Water Resources and organizations (2nd revised) |
JUL-19 JUN-27 |
5,409.42 5,371.24 |
On Going | ||||
| LAND RECLAMATION | Madhumati-Navaganga Sub-Project Rehabilitation and Rejuvenation and Ecological Rebalancing of Navaganga River through Reclamation/Dredging Project (1st Revised) |
DEC-19 JUN-27 |
34,275.33 29,241.38 |
NARAIL | LOHAGARA | Narail-2 | On Going | Download |
| BANK PROTECTION | Bank Protective Work along the Both Bank of Kushiyara River in front of Bibiyana Power Plants in Habiganj District (1st Revised) |
JUN-20 JUN-27 |
54,173.64 45,045.34 |
HABIGANJ | BAHUBAL, BANIACHONG, LAKHAI, MADHABPUR, NABIGANJ | Habiganj-1, Habiganj-2, Habiganj-3, Habiganj-4 | On Going | Download |
| BANK PROTECTION | River Bank Protection work along the Right and Left Bank of Dharla River with Flood Control in Kurigram Sadar, Rajarhat & Fulbari Upazila in Kurigram District. (1st Revised) |
JUN-20 DEC-27 |
62,945.28 47,280.88 |
KURIGRAM | KURIGRAM SADAR, PHULBARI, RAJARHAT | Kurigram-2 | On Going | Download |
| BANK PROTECTION | Protection Project at Moulvibazar sadar, Rajnagar and Kulaura upazilla from erosion of Monu River. |
JUL-20 JUN-28 |
99,628.00 56,657.97 |
MOULVIBAZAR | KULAURA, MAULVIBAZAR SADAR, RAJNAGAR | Moulvibazar-2, Moulvibazar-3 | On Going | Download |
| OTHERS | Char Development and Settlement Project-Bridging (Additional Financing) (BWDB Part) (1st Revised) |
AUG-20 JUN-27 |
31,159.18 18,469.54 |
NOAKHALI | COMPANIGANJ, HATIYA, KABIRHAT, SUBARNACHAR | Noakhali-4, Noakhali-5, Noakhali-6 | On Going | Download |
| BANK PROTECTION | Removal of Drainage Congestion from Kopotakkho River Basin (Phase-2) (1st Revised) |
SEP-20 JUN-27 |
50,158.51 36,982.94 |
JASHORE, JHENAIDAH, KHULNA, SATKHIRA | ASSASUNI, CHAUGACHHA, JHIKARGACHHA, KALAROA, KESHABPUR, KOTCHANDPUR, KOYRA, MAHESHPUR, MANIRAMPUR, PAIKGACHHA, TALA | Jashore-2, Jashore-5, Jashore-6, Jhenaidah-3, Khulna-6, Satkhira-1, Satkhira-3 | On Going | Download |
| BANK PROTECTION | Protection of Dhulia launchghat, Baupal Upazilla, Patuakhali District to Durgapasha of Bakergonj Upazilla in Barisal District from erosion of Tetulia river. (1st Revised) |
SEP-20 JUN-27 |
74,802.63 66,860.63 |
BARISHAL, PATUAKHALI | BAKERGANJ, BAUPHAL | Barishal-6, Patuakhali-2 | On Going | Download |
| DRAINAGE | Bhairob River Re-excavation Project (2nd Phase) (1st Revised) |
NOV-20 JUN-27 |
27,307.35 25,402.50 |
CHUADANGA, MEHERPUR | CHUADANGA SADAR, DAMURHUDA, MUJIB NAGAR | Chuadanga-1, Chuadanga-2, Meherpur-1 | On Going | Download |
| BANK PROTECTION | Protection of Katlamari area at Fulchari Upazila, Gobindi &Holdia area at Saghata Upazila from erosion of Jamuna River in Gaibandha District (1st Revised) |
JAN-21 DEC-26 |
83,096.76 68,162.45 |
GAIBANDHA | FULCHHARI, SAGHATA | Gaibandha-5 | On Going | Download |
| BANK PROTECTION | Protection of Daulatkhan Pouroshova, Chokighat and other more valuable area from the erosion of the Meghna River in Bhola District (1st Revised) |
APR-21 JUN-27 |
55,738.69 49,813.81 |
BHOLA | BURHANUDDIN, DAULAT KHAN | Bhola-2 | On Going | Download |
| OTHERS | Command Area Development and extension of Teesta Irrigation Project |
JUN-21 DEC-26 |
145,233.00 86,685.36 |
DINAJPUR, NILPHAMARI, RANGPUR | BADARGANJ, CHIRIRBANDAR, DIMLA, GANGACHARA, JALDHAKA, KHANSAMA, KISHOREGANJ, NILPHAMARI SADAR, PARBATIPUR, RANGPUR SADAR, SAIDPUR, TARAGANJ | Dinajpur-4, Dinajpur-5, Nilphamari-1, Nilphamari-2, Nilphamari-3, Nilphamari-4, Rangpur-1, Rangpur-2, Rangpur-3 | On Going | Download |
| BANK PROTECTION | Protection work at the bank of Meghna river at Borokheri, Ludhuabazar and kader ponditer hat areas in Ramgoti and Kamal Nagar upazila under Lakshmipur District |
JUL-21 DEC-26 |
308,996.99 184,728.79 |
LAKSHMIPUR | KAMALNAGAR, RAMGATI | Lakshmipur-4 | On Going | Download |
| OTHERS | Rehabilitation of Tangoan Barage, Buri Bundh and Bhully Bundh Irrigation Projects, River Bank Protection and Construction of Combined Water Control Structure at Thakurgaon District (1st Revised) |
JUL-21 DEC-26 |
33,625.13 25,783.75 |
THAKURGAON | THAKURGAON SADAR | Thakurgaon-1 | On Going | Download |
| BANK PROTECTION | Flood control, Drainage and Irrigation Project in Patiya Upazilla in Chittagong District |
AUG-21 JUN-27 |
115,836.00 53,837.05 |
CHATTOGRAM | PATIYA | Chattogram-12 | On Going | Download |
| BANK PROTECTION | Bank Protective Work along the Left Bank of Padma River down of Padma Multipurpose Bridge in Louhajong and Tongibari Upazila at Munshigonj District (2nd Revised) |
OCT-21 SEP-26 |
52,750.00 45,490.66 |
MUNSHIGANJ | LOHAJANG, TONGIBARI | Munshiganj-2 | On Going | Download |
| OTHERS | Management and Improvement of Dudhkumar River Flowing through the Kurigram District |
OCT-21 JUN-27 |
69,214.59 49,701.78 |
KURIGRAM | BHURUNGAMARI, KURIGRAM SADAR, NAGESHWARI | Kurigram-1, Kurigram-2 | On Going | Download |
| OTHERS | Rehabilitation of Polder No. 15 in Satkhira District (1st Revised) |
OCT-21 JUN-27 |
102,017.00 65,008.01 |
SATKHIRA | SHYAMNAGAR | Satkhira-4 | On Going | Download |
| BANK PROTECTION | Disaster Risk Management Extension Project (Component-I, BWDB Part) (1st Revised) |
DEC-21 JUN-27 |
89,675.22 67,113.18 |
BAGERHAT, KHULNA, SATKHIRA | ASSASUNI, BAGERHAT SADAR, BATIAGHATA, DACOPE, DIGHALIA, KALIGANJ, KHALISHPUR, KOYRA, MORRELGANJ, PAIKGACHHA, SHYAMNAGAR | Bagerhat-2, Bagerhat-4, Khulna-1, Khulna-3, Khulna-4, Khulna-6, Satkhira-3, Satkhira-4 | On Going | Download |
| LAND RECLAMATION | Climate Smart Agriculture and Water Management Project (BWDB part) |
DEC-21 JUN-27 |
118,255.00 27,355.14 |
On Going | Download | |||
| BANK PROTECTION | Rehabilitation of Polders 43/1 and 44B under Barguna District and Protection of Vulnerable Area from Payra River Erosion Project (1st Revised) |
JAN-22 JUN-27 |
71,225.00 36,985.17 |
BARGUNA | AMTALI | Barguna-1 | On Going | Download |
| OTHERS | Rehabilitation Project of Polder No-14/1 of Khulna District |
JAN-22 DEC-26 |
117,231.25 49,184.39 |
KHULNA | KOYRA | Khulna-6 | On Going | Download |
| REHABILATATION | Rehabilitation of Coastal Embankment, Development of Drainage System and Bank Conservation at Mujib Nagar and Manpura in Bhola District (Phase 1) (1st Revisrd) |
APR-22 JUN-27 |
111,700.00 82,930.20 |
BHOLA | CHAR FASSON, MANPURA | Bhola-4 | On Going | Download |
| BANK PROTECTION | Rehabilitation of Polder No. 41/6A and 41/6B and 41/7A under Barguna District and protection of other vulnerable areas including Bishkhali and Payra River from erosion of Betagi town. |
APR-22 MAR-28 |
82,649.25 30,961.33 |
BARGUNA | BARGUNA SADAR, BETAGI | Barguna-1, Barguna-2 | On Going | Download |
| BANK PROTECTION | Riverside protection works, wave protection and canal re-excavation projects in 10 upazilas of Kishoreganj district (1st Revised) |
JUN-22 DEC-26 |
64,185.22 55,799.07 |
KISHOREGANJ | KISHOREGANJ SADAR | Kishoreganj-1 | On Going | Download |
| BANK PROTECTION | Rehabilitation of Coastal Embankments, Development of Drainage System and Conservation of Banks in Tajumuddin and Lalmohan Upazilas (Phase 1) (1st Revised) |
JUN-22 JUN-27 |
110,000.00 83,105.65 |
BHOLA | LALMOHAN, TAZUMUDDIN | Bhola-3 | On Going | Download |
| BANK PROTECTION | Conservation of Morelganj Upazila Sadar and adjacent areas of Bagerhat District from Panguchi River break and Bishkhali River Re-Dredging Project |
JUL-22 JUN-27 |
65,883.18 30,434.91 |
BAGERHAT | MORRELGANJ | Bagerhat-4 | On Going | Download |
| BANK PROTECTION | Irrigation and Drainage Development Project of Purbadhala Upazila of Netrakona District |
JUL-22 JUN-27 |
17,631.50 13,716.28 |
NETROKONA | PURBADHALA | Netrokona-5 | On Going | Download |
| BANK PROTECTION | Protection of Khagrachari city and adjacent infrastructure from river erosion. |
AUG-22 JUN-28 |
62,216.75 28,634.91 |
KHAGRACHHARI, RANGAMATI | DIGHINALA, GUIMARA, KHAGRACHHARI SADAR, LANGADU, MAHALCHHARI, NANIARCHAR, PANCHHARI | Khagrachhari, Rangamati | On Going | Download |
| BANK PROTECTION | Barisal Cantonment Area Protection Project from Erosion of Factories, Bighai and Payra Rivers in Barisal District (Phase 1) |
APR-23 DEC-26 |
67,600.00 33,694.60 |
BARISHAL | BARISHAL SADAR (KOTWALI) | Barishal-5 | On Going | Download |
| BANK PROTECTION | Construction of Multipurpose Hydraulic Elevator DAM in Shrimai Canal of Patia Upazila of Chittagong District. |
APR-23 JUN-27 |
13,303.00 5,496.35 |
CHATTOGRAM | PATIYA | Chattogram-12 | On Going | Download |
| IRRIGATION | Rehabilitation of Meghna-Dhangoda Irrigation Scheme and conservation of river banks. |
APR-23 JUN-27 |
34,765.69 21,559.30 |
CHANDPUR | MATLAB UTTAR | Chandpur-2 | On Going | Download |
| FLOOD CONTROL | Flood Reconstruction Emergency Assistance project (1st Revised) |
JUN-23 JUN-27 |
74,826.35 53,736.34 |
SUNAMGANJ, SYLHET | BALAGANJ, BEANI BAZAR, BISHWAMBARPUR, BISHWANATH, CHHATAK, COMPANIGANJ, DERAI, DHARAMPASHA, DOWARABAZAR, FENCHUGANJ, GOLAPGANJ, GOWAINGHAT, JAGANNATHPUR, JAINTIAPUR, JAMALGANJ, KANAIGHAT, SHANTIGANJ (DAKSHIN SUNAMGANJ), SULLA, SUNAMGANJ SADAR, SYLHET SADAR, TAHIRPUR, ZAKIGANJ | Sunamganj-1, Sunamganj-2, Sunamganj-3, Sunamganj-4, Sunamganj-5, Sylhet-1, Sylhet-2, Sylhet-3, Sylhet-4, Sylhet-5, Sylhet-6 | On Going | Download |
| BANK PROTECTION | Conservation and dredging of Shaheed Birshrestha Munshi Abdur Rauf Memorial Museum and other areas including road connection from the left bank of Madhumati river in Faridpur district. |
JUN-23 JUN-27 |
48,675.64 37,966.33 |
FARIDPUR | ALFADANGA, MADHUKHALI | Faridpur-1 | On Going | Download |
| BANK PROTECTION | Charkaua, Chandmari, Jagua, Lamchari and Charmonai areas in Sadar Upazila of Barisal District against Kirtankhola River Erosion Protection Project (1st Phase) |
JUN-23 JUN-27 |
51,292.00 39,996.15 |
BARISHAL | BARISHAL SADAR (KOTWALI) | Barishal-5 | On Going | Download |
| BANK PROTECTION | Project to protect the Mazhirghat zero point area from the breach of the right bank of Padma river in Jazira upazila of Shariatpur district. |
SEP-23 JUN-27 |
120,243.53 58,028.96 |
SHARIATPUR | ZANJIRA | Shariatpur-1 | On Going | Download |
| OTHERS | Conservation of slope with permanent rehabilitation of damaged dam of Polder No. 72 in Sandwip Upazila of Chittagong District |
SEP-23 JUN-27 |
56,221.00 5,306.75 |
CHATTOGRAM | SANDWIP | Chattogram-3 | On Going | Download |
| OTHERS | Uri Char-Noakhali Cross Dam construction project aimed at land reclamation |
SEP-23 JUN-27 |
58,894.00 24,082.18 |
NOAKHALI | COMPANIGANJ, SUBARNACHAR | Noakhali-4, Noakhali-5 | On Going | Download |
| BANK PROTECTION | Implementation of protective works to protect infrastructures built on canals in Hatia Upazila of Noakhali District from the Meghna River breach. |
OCT-23 JUN-26 |
37,804.54 8,923.81 |
NOAKHALI | HATIYA | Noakhali-6 | On Going | Download |
| BANK PROTECTION | Aymon river reclamation and riverbank conservation in Muktagachha upazila of Mymensingh district |
OCT-23 JUN-25 |
4,695.00 3,065.04 |
MYMENSINGH | FULBARIA, MUKTAGACHHA | Mymensingh-5, Mymensingh-6 | On Going | Download |
| FLOOD CONTROL, DRAINAGE AND IRRIGATION | Integrated water resource management implementation project for Tungipara-Kotalipara upazila of Gopalganj district |
OCT-23 DEC-28 |
89,355.05 4,261.01 |
BARISHAL, GOPALGANJ, MADARIPUR | AGAILJHARA, GOPALGANJ SADAR, KOTALIPARA, RAJOIR, TUNGIPARA | Barishal-1, Gopalganj-2, Gopalganj-3, Madaripur-2 | On Going | Download |
| BANK PROTECTION | Rehabilitation of Flood Control Dam (Jiwan Raksha Dam) in Raipur Union of Sadar and Barhatta Upazila of Netrokona District and implementation of defense works to prevent erosion of Kangs river. |
NOV-23 DEC-25 |
4,770.00 2,690.10 |
NETROKONA | BARHATTA, NETROKONA SADAR | Netrokona-2 | On Going | Download |
| BANK PROTECTION | Project to protect the old Hijla, Baushia and Harinathpur areas under Hijla upazila from the collapse of Meghna branch river. |
NOV-23 JUN-27 |
62,886.00 12,186.04 |
BARISHAL | HIZLA | Barishal-4 | On Going | Download |
| BANK PROTECTION | Protection of Talbaria under Mirpur upazila of Kushtia district and Komarkandi area of Shilaidah union under Kumarkhali upazila from the breach of Padma river. |
NOV-23 DEC-26 |
147,198.00 40,329.31 |
KUSHTIA | KUMARKHALI, MIRPUR | Kushtia-2, Kushtia-4 | On Going | Download |
| REHABILATATION | Rejuvenation of Ichamati River in Pabna District |
DEC-23 JUN-27 |
155,490.00 7,434.40 |
PABNA | ATGHARIA, BERA, ISHWARDI, PABNA SADAR, SANTHIA | Pabna-1, Pabna-4, Pabna-5 | On Going | Download |
| BANK PROTECTION | Re-excavation of Shubhadha Canal under Keraniganj Upazila of Dhaka District and Development and Protection Project of both banks of the canal (1st Phase) |
DEC-23 JUN-26 |
31,759.00 8,136.75 |
DHAKA | KERANIGANJ | Dhaka-3 | On Going | Download |
| FLOOD CONTROL AND DRAINAGE | Implementation of protective works to protect various places of Feni River and Chhota Feni River under Sonagazi and Daganbhuiya Upazilas of Feni District from bank erosion. |
DEC-23 JUN-26 |
4,895.00 1,132.61 |
FENI | DAGANBHUIYAN, SONAGAZI | Feni-3 | On Going | Download |
| BANK PROTECTION | Conservation Rehabilitation of Chadmpur City |
DEC-23 JUN-27 |
82,702.00 11,836.93 |
CHANDPUR | CHANDPUR SADAR | Chandpur-3 | On Going | Download |
| BANK PROTECTION | Protection of various areas of Sadar Upazila and Nalchiti Upazila of Jhalkathi District from the erosion of Sugandha River |
JAN-24 JUN-27 |
68,036.00 9,402.51 |
JHALOKATHI | JHALOKATI SADAR, NALCHITY | Jhalokathi-2 | On Going | Download |
| BANK PROTECTION | Bhola Sadar Upazila Protection Project from Meghna River Eruption |
JAN-24 JUN-27 |
68,910.00 10,487.01 |
BHOLA | BHOLA SADAR | Bhola-1 | On Going | Download |
| BANK PROTECTION | Implementation of permanent river bank protection works on the right and left banks of the transboundary Someshwari river in Durgapur upazila in Netrakona district. |
APR-24 JUN-26 |
4,588.00 818.17 |
NETROKONA | DURGAPUR | Netrokona-1 | On Going | Download |
| BANK PROTECTION | Mansoor Ahmed Women's College, Ispinjapur and Gopalpur markets in Barhatta upazila of Netrakona district, conservation of Kangsh river banks |
JUN-24 JUN-26 |
4,400.00 |
NETROKONA | BARHATTA | Netrokona-2 | On Going | Download |
| RIVER DREDGING | Protection of Rasulpur village and re-dredging of the river from Kachamatia river breach in Nandail upazila in Mymensingh district. |
JUN-24 JUN-26 |
4,881.00 929.12 |
MYMENSINGH | NANDAIL | Mymensingh-9 | On Going | Download |
| LAND RECLAMATION | Sustainable Water Management Project in Banshkhali and Anwara Upazilas of South Chittagong (1st Phase) |
JUL-24 JUN-27 |
87,457.00 6,497.64 |
CHATTOGRAM | BANSHKHALI | Chattogram-16 | On Going | Download |
| OTHERS | Feasibility study update of North Rajshahi Irrigation Project and feasibility study of rehabilitation work of existing light irrigation projects in Dinajpur, Thakurgaon and Panchagarh districts |
JUL-24 JUN-26 |
968.80 2.41 |
On Going | ||||
| OTHERS | Feasibility study of basin-based water management project for rivers in Barisal region |
JUL-24 JUN-26 |
999.00 2.91 |
On Going | ||||
| BANK PROTECTION | Bank conservation work to prevent the erosion of Karnaphuli river and connected canals under Boalkhali upazila of Chittagong district. |
JUL-24 DEC-26 |
13,409.00 2,022.38 |
CHATTOGRAM | BOALKHALI | Chattogram-8 | On Going | Download |
| BANK PROTECTION | Jamuna River Sustainable Management Project-1: River Bank Protection and River Management (Component-1) |
OCT-24 DEC-27 |
87,328.00 49.84 |
GAIBANDHA, TANGAIL | FULCHHARI, KALIHATI | Gaibandha-5, Tangail-4 | On Going | Download |
| BANK PROTECTION | Implementation of defense work on the Matamuhuri River to protect Lamabazar in Lama Upazila of Bandarban district |
JAN-25 JUN-26 |
3,352.00 13.47 |
BANDARBAN | LAMA | Bandarban | On Going | Download |
| TOWN PROTECTION | Protection of launch ghat, ferry ghat and adjacent areas adjacent to Indurhat Port on the right bank of Sandhya River under Nesarabad (Swarupkathi) Upazila of Pirojpur District |
JAN-25 DEC-26 |
4,726.00 364.58 |
PIROJPUR | NESARABAD (SWARUPKATI) | Pirojpur-1 | On Going | Download |
| OTHERS | Bangladesh Sustainable Recovery, Emergency Preparednee and Response Project (B-Strong) (BWDB Part) |
JUL-25 JUN-29 |
59,972.23 |
BRAHMANBARIA, CUMILLA, FENI, LAKSHMIPUR, NOAKHALI | AKHAURA, BURICHANG, CHHAGALNAIYA, COMPANIGANJ, CUMILLA ADARSHA SADAR, DAGANBHUIYAN, DAUDKANDI, FENI SADAR, FULGAZI, HATIYA, LAKSHMIPUR SADAR, MURADNAGAR, PARSHURAM, RAMGATI, ROYPUR, SONAGAZI, SUBARNACHAR, TITAS | Brahmanbaria-4, Cumilla-1, Cumilla-2, Cumilla-3, Cumilla-5, Cumilla-6, Feni-1, Feni-2, Feni-3, Lakshmipur-2, Lakshmipur-3, Lakshmipur-4, Noakhali-4, Noakhali-5, Noakhali-6 | On Going | Download |
| OTHERS | Expansion of irrigation facilities by quickly resolving waterlogging in Bhabadah and adjacent beel areas |
JUL-25 JUN-27 |
4,541.00 |
JASHORE | JASHORE SADAR | Jashore-3 | On Going | |
| BANK PROTECTION | Re-excavation of Dhaleshwari and Lauhajang rivers under Tangail district and river bank protection work in Tangail municipal area |
OCT-25 JUN-27 |
4,795.30 |
TANGAIL | TANGAIL SADAR | Tangail-5 | On Going | |
| BANK PROTECTION | Development of flood management and drainage system in Bamni River Basin of Noakhali District |
OCT-25 JUN-27 |
4,799.54 |
NOAKHALI | NOAKHALI SADAR | Noakhali-4 | On Going | |
| BANK PROTECTION | Defense of the right bank of the Dholbhanga River in Bancharampur Upazila of Brahmanbaria District and the right bank of the Lower Titas River in Ujanchar Union |
OCT-25 JUN-27 |
4,212.98 |
BRAHMANBARIA | BANCHHARAMPUR | Brahmanbaria-6 | On Going | |
| DRAINAGE | Mahananda River Dredging and Rubber Dam Construction Project in Sadar Upazila of Chapainawabganj District (3rd Revised) |
OCT-25 JUN-27 |
4,846.70 |
CHAPAI NAWABGANJ | CHAPAI NABABGANJ SADAR | Chapainawabganj-3 | On Going | |
| OTHERS | Magra River Revitalization Project under Netrakona District |
NOV-25 JUN-27 |
4,849.70 |
On Going | ||||
| REHABILATATION | Revitalization and depollution of Sutang River in Habiganj District |
NOV-25 DEC-27 |
4,774.62 |
On Going | ||||
| OTHERS | Salta River Revitalization, Pollution-Free and Encroachment-Free Project in Khulna District |
DEC-25 JUN-27 |
2,273.62 |
On Going | ||||
| BANK PROTECTION | Protecting various areas of Mehendiganj Upazila of Barisal district from erosion of Tentulia River |
JAN-26 JUN-29 |
73,988.00 |
BARISHAL | MEHENDIGANJ | Barishal-4 | On Going | |
| OTHERS | Waterlogging and irrigation system development through re-drainage of Hisna and Sagarkhali rivers in Kushtia district |
JAN-26 DEC-27 |
4,884.00 |
On Going | ||||
| OTHERS | Emergency maintenance and rehabilitation of Ganga Kapotaksha Irrigation Project |
JAN-26 JUN-29 |
129,996.91 |
On Going | ||||
| OTHERS | Surma-Kushiyara River Basin Development and Flood and Integrated Water Resources Management Project |
JAN-26 JUN-28 |
127,377.03 |
On Going | ||||
| OTHERS | Waterlogging of beels and residential areas adjacent to the Sholmari River in Dumuria and Batiaghata upazilas of Khulna district |
JAN-26 JUN-28 |
4,826.65 |
KHULNA | BATIAGHATA, DUMURIA | Khulna-1, Khulna-5 | On Going | |
| LAND RECLAMATION | Protection of coastal polder No. 39/2D from erosion of Baleshwar River in Boro Machua Rocketghat area of Mathbaria upazila of Pirojpur district |
JAN-26 JUN-28 |
4,644.58 |
PIROJPUR | MATHBARIA | Pirojpur-3 | On Going | |
| OTHERS | Feasibility study project on sustainable management of rivers in Dinajpur district |
JAN-26 APR-28 |
441.61 |
On Going | ||||
| BANK PROTECTION | Bank protection and Nagda canal re-excavation to protect both banks of Turag River in Gazipur district from erosion |
JAN-26 DEC-28 |
3,900.61 |
On Going | ||||
| OTHERS | Sustainable Water Management Project of Karnaphuli and Associated Rivers (Kachalong, Raikhyang and Shalak Rivers) in Rangamati Hill District |
JAN-26 JUN-30 |
68,739.00 |
On Going | ||||
| OTHERS | Re-excavation, pollution-free and encroachment-free of the Baronai River in Rajshahi and Natore districts |
JAN-26 JUN-28 |
4,650.12 |
On Going | ||||
| OTHERS | Rejuvenating, encroaching and pollution-free Bankkhali River in Cox's Bazar district |
JAN-26 JUN-28 |
4,750.80 |
On Going | ||||
| OTHERS | Rejuvenation of Alaikuri River in Rangpur District |
JAN-26 JUN-28 |
3,180.11 |
On Going | ||||
| LAND RECLAMATION | Integrated management of water and land resources to improve the quality of life in the Arial Beel area (BWDB section) |
JAN-26 JUN-30 |
34,084.96 |
On Going | ||||
| BANK PROTECTION | Conservation of both banks of the Padma River in Chapainawabganj district (Part 1) |
FEB-26 DEC-29 |
74,806.00 |
On Going | ||||
| OTHERS | Sustainable management of rivers in Panchagarh and Thakurgaon districts (Part 1) |
FEB-26 DEC-29 |
67,880.00 |
On Going | ||||
| OTHERS | Project Preparatory Study for Metro Dhaka Water Security and Resilience Program (Turag, Tongi Canal, Balu and Shitalakshya Rivers) (Bapaubo Component) |
JUL-26 JUN-27 |
1,544.00 |
On Going | ||||